Purpose:
Bærum municipality establishes a new storm water main
through the area of Jar. The area is known for
sensitive quick clay.
Design:
A trench of over 500 m was lime stabilised. It was
set KS piles in ribs and single piles.
Execution:
The area was stabilized with Multicem 50/50 and a
mixing quantity 100 kg/m³. Challenging
project with being long and sometimes narrow
streets in Bærum. The work was done closely with neighbors and
elementary school. In addition, there was quick clay and lots of it
consideration had to be given to the project. The work was done
know the help of a KC rigger.
The work was first carried out under the auspices of Consto Dambygg
transferred to Seabrokers Fundamentering AS in 2022
and the work was completed.