Design:
An area of approximately 5,400 m² was lime stabilised. KS piles were installed in ribs and as single piles
Execution:
The area was stabilized with Multicem 50/50 and a mixing quantity of 100 kg/m³. Due to the great danger of pore pressure build-up, there was a lot of moving of rigs in the area. The work was carried out using two KC rigs.
KS-peler: 3655 stk, diam. Ø700mm, lengde 25m eller til fjell. Totalt 66 408 lm med innblanding og 2 291 tonn kalk.
Runar Nykvist, Skanska Norge AS