Challenges:
Narrow construction site with little storage space for pipes
the facility
The pipes had to be unloaded in one area about 2 m from
construction site
The pile tips were also welded on to the pipes
this area and transported to the construction site
as required.
To reduce noise in the sea due to spawning fish
we had to use a double air curtain around the piles
during framing of piles

LokalitetÅrdal
UtførendeSeabrokers Fundamentation Seapiling
MetoderPiling
Varighet2023
Omfang
  • Scope
    Framing of 16 pile tubes Ø914×16.
    Lengths from 23 m to 50 metres
    Total quantities of pipes delivered
    683.7. Total quantities of affected piles
    624 meters
Referansekontakt

Reference contact
Birken og Co AS