Orientation about the project

Stortingsgaten 6 is a new office complex on 7 floors and a car park on 3 floors below

listing. The 975m plot is bounded by Stortingsgata, Rosenkrantzgata and Prestegata

as well as the neighboring building in Stortingsgata 4. Originally there were two buildings on the site;

Flaggfabrikken and Nordstjernegården. The flag factory dates from 1895 and is listed.

Extensive renovation work was initiated to preserve the facade. The building was

reimbursed with steel core piles for mountains. In connection with these works was built

inflicted settlement damage on the facade with the consequence that the facade facing the backyard was

demolished.

Basic conditions

No basic investigations had been carried out on the property itself, other than a summary of it

existing information about the ground conditions around Stgt. 6. After Nordstjernegården

had been demolished, it was only possible to carry out ground investigations. What was originally thought

mountain level elevation -05 and -1.0 turned out to be the top of a powerfully permeable moraine layer.

The depth to the rock was between elevation -4 and -15. The groundwater was at level 2.

Problem statement

In consideration of nearby buildings, it was necessary to have a tight design

the construction pit. On the basis of trial framing, brace-anchored piling to rock was chosen as

primary safety construction of the construction pit. However, it proved difficult to hit

piled down to the mountain, and only a few pile needles reached down.

Solution

When it was revealed that Stgt. 4 did not stand on mountains, jet piles were chosen both as load carriers

construction solution for Stgt. 4 and as a seal in the moraines overfjell. For sealing sheet piling

it chose jet piles as the sealing method. The piles were installed 60cm down into the rock and up 1.0m above

sheet piling.

Pore ​​pressure and settlement measurements

Four pore pressure measurements were installed prior to excavation below the groundwater level. After

each time it was excavated, measured pore pressure converted to rise height showed a level corresponding to

medium excavation level. This also confirmed that there was a lot of inflow into the construction pit

insignificant. Stortingsgata 4 was followed up with continuous settlement measurements. No

sentences were recorded, neither during the jet pile works nor later during excavation of

the construction pit. However, the flag factory in Prestegata put up to 43mm in connection

with reimbursement with steel core piles.

Conclusion

Despite trial fitting of piles to rock, problems can arise. Alternative solutions must

considered in the design phase. Jet piles can be used in combination with sealing and

structural elements.

LokalitetPorsgrunn
UtførendeJetgrunn
MetoderFoundations of buildings with jet piles
VarighetByggeår 2002
Referansekontakt

OBAS