Orientation about the project

The project included the execution of a new casting shaft for Norsk

Hydro, Upper Årdal. The construction which has a circular shape,

has an internal diameter of 9 meters and a length of 27

meters under the floor in the existing hall. It was required that

there was to be full operation in the hall during the entire construction period,

which meant very little space for construction equipment. A crane

who constantly passed over the workplace also asked very much

strict safety requirements. The shaft is also placed all the way in

to a heavily loaded foundation at a depth of 2.2 meters below

floor level. The requirement for tremors/vibrations and sentences was 0.

Basic conditions

Glacifluvial delta masses with similar frictional masses.

Groundwater level approx. 5 meters below floor level.

 

Problem statement

The casting shaft is the country’s deepest, and is circular with a

internal net total height of 25 metres. The requirement for

the pile construction was to be a permanent one

unreinforced and dense concrete construction which was designed so that

there should be no stretch marks or unacceptable areas

shear forces. The construction is also influenced by large exteriors

earth and water pressure.

The construction project had a very high degree of difficulty and

therefore set very strict requirements for quality and execution.

The construction belongs to safety class 3 and associated

high requirements for control of calculations and execution.

Solution

The construction project was solved using the J-2 method with

the following arguments for choosing the method:.

  • that there was good documented certainty that

the method was feasible in the relevant cases

masses and high water pressure – that you could

maintain full production in the foundry premises

during the entire construction period

  • that adjacent constructions were not applied

any kind of phrases, shakes or

vibrations

  • that the method eliminated many

work processes that would otherwise be involved

conventional methods

  • that the costs were far more predictable than

by other solutions

LokalitetÅrdal
UtførendeJetgrunn
MetoderEstablishment of permanent construction, including responsibility for the method, equipment, technical the execution, control, quality assurance as well documentation
VarighetByggeår 1998/1999
Referansekontakt

Norsk Hydro ASA, Årdal
Metallverk