Orientation about the project

Refoundation of the Vestbanen in Oslo with jet piles (J2-

method). The building is today listed. Restrictions imposed by

Byatikvaren was large and challenging.

Foundation conditions

The Vestbane building is founded with hewn foundation walls

natural stone. The south wing is founded on mountains, while

The arrivals hall and the north wing are based on wooden rafters.

The raft was heavily attacked by rot in some places.

The floor construction inside the access hall consists of vaulted ceilings.

These are based on stone foundations on wooden rafts i

crawl space and takes up floor loads and column loads from the structures

above 1st floor level. Three of the foundations were characterized as i

very poor constitution. The Vestbane building was partially affected

major settlement damage, especially in the column and arch structures.

Basic conditions

The ground consists of medium firm clay over mountains with assumed

shear strength of 50kPa and bulk density of 20kN/m2. The elevation varies

from 0 to -12. It is shallowest to the mountains in the south with increasing depth towards

north-west. The groundwater level is approx. at elevation + 0.26.

 

Solution options

In the preliminary project phase, two reimbursement methods were considered: 1)

Drill down steel posts on each side of the walls and then install

ride through that spans from pile to pile. 2) Use Jet-pel

the method.

Selected solution

The project group recommended a solution with jet piles. The reason was

based on the following points: Great predictability with regard to

quality and execution. Minimal sentences and good in-situ control

any deformations that may occur underneath

the refunding works, so that corrective measures could be taken

be implemented immediately. No vibrations/shakes that can

cause secondary damage to the building structure. It won’t

reinforcements of the gray stone walls may be necessary. All

the walls will receive direct support (contact moulding). Large portions

of the works can be carried out from the outside of the building, with the exception of

the internal foundations of the building. The execution will require small

interventions in the constructions and will therefore be in line with

the conservation decision. All interior work can be carried out from 1.

floor plan. Great flexibility, low uncertainty/risk.

Sentences/raises

Accumulated sentences are not larger than +/- 3mm. But with one

stated measurement accuracy of +/- 2mm is therefore minimal

deformations of the floor and column construction.

LokalitetOslo
UtførendeJetgrunn
MetoderEstablishment of permanent construction, including responsibility for the method, equipment, technical execution, control, quality assurance and documentation
VarighetByggeår 2003
Referansekontakt

Statsbygg